| Timeline
for construction of your home. |
 |
Site work and Excavation |
| |
|
Layout lot |
| Call
Blue Stakes to mark Utilities |
| Clear site
|
| Excavate hole and build roads |
 |
Concrete footings
|
| |
|
Form footings |
| Call for footing inspection |
| Pour footings |
| Strip footings |
 |
Concrete foundation |
| |
 |
Form foundation |
| |
Foundation inspection
|
| Pour foundation
|
| Strip foundation forms |
| Waterproof foundation |
 |
Install window wells |
 |
Underground work |
| |
|
Install sewer and waterlines |
| Underground plumbing |
| Underground heating |
| Underground electrical |
| Final grade for basement floor |
 |
Concrete flat work |
| |
|
Backfill and settle garage floor |
| Pour basement floor |
| Pour garage floor |
 |
Backfill foundation |
 |
Rough framing |
|
|
Frame basement walls |
| Floor framing |
| Frame exterior walls |
| Frame interior walls |
| Set roof trusses and plywood |
 |
Windows and exterior doors
|
|
|
 |
Roofing |
| |
 |
Dry in roof with felt |
 |
Shingle roof |
 |
Rough plumbing, HAVC, electrical |
| |
|
Rough in HAVC |
| Rough in plumbing |
| Rough in electrical |
| Four way inspection |
| Make any corrections
from inspection |
 |
Reinspection |
 |
Insulation |
| |
 |
Insulate floors and walls |
 |
Insulation inspection |
 |
Exterior finishes |
| |
|
Siding, soffit, and
facia |
| Gutters and
downspouts |
| Stucco brick or Rock
exterior |
 |
Exterior flat work |
 |
Drywall work |
| |
|
Hang sheet rock |
| Nail inspection |
 |
Tape and texture |
 |
Finish work |
| |
|
Install interior
doors
|
| Install shelving |
| Install all interior
moldings |
| Install finish stair
treads |
| Install handrail,
fireplace mantle, etc. |
 |
Install garage doors |
 |
Painting |
| |
|
Paint exterior doors
etc. |
| Prep and finish
handrail
|
| Prep all trim work |
| Prime woodwork |
| Prime sheet rock |
| Paint woodwork |
 |
Paint walls and ceilings |
 |
Interior finish |
| |
 |
Install tile, cultured marble,
etc in showers and tubs |
| |
Blow in attic
insulation
|
| Install cabinets |
| Install counter tops
and vanities |
| Install wood, tile,
etc floors |
| Touch up finish work
and paint |
| Finish electrical and
hang light fixtures |
| Finish HAVC |
| Finish plumbing |
| Install carpets |
| Hardware &
Installation |
| Install appliances |
| Shower Doors &
Mirrors |
| Final Grade |
| Plaster foundation
|
 |
Clean house, windows etc |
 |
Final inspection and punch list |
| |
|
Final inspection |
| |
Complete punch list |
| |
Final reinspection |
| |
 |
Certificate of occupancy
|